BMW N63 Valve Cover Gasket Replacement
Fits these US N63 BMWs
F10 550i, E70 X5 50i, and F01 750i. Build date picks N63, N63N, or N63O1 gasket numbers.
- Cover torque
- 10 Nm
- Perimeter bolts
- 17 (N63) / 16 (N63O1)
- Sensor release
- 90 degrees
What this job fixes
Renew profile gaskets and related seals on both banks of the N63 V8. Left bank: cylinders 5-8. Right bank: 1-4. Finish one bank before the other. N63O1 builds need cat and vacuum pump work before the cover bolts.
A gasket set fixes a leak at the cover edge. Buy the whole cover if yours is cracked or, on engines with the PCV valve built into the cover, the PCV has failed.
BMW gives no mileage rule for a valve cover leak. A light oil film from sweating needs no repair. Pooling, dripping or spots under the BMW mean an active leak, which shows as a burning oil smell, smoke off the exhaust and oil in the spark plug wells.
Before you start
Disconnect the battery before high-pressure fuel work and keep a battery charger off the jump-start terminal. Wait until coolant is below 40 degrees C before you open HP fuel lines. Wear PPE: fuel can discharge at high speed when a line pops loose. Seal every open fuel line with a lock cap. On the right bank, drain the cooling system before you open lines near the engine. Remove the acoustic cover only above 20 degrees C; at reinstall use distilled water on the seal, not grease.
What you replace
Profile gaskets, general
Send us your VIN and we'll send yours.
E70 X5 50i profile gaskets
11 12 7 566 288 (11127566288)
11 12 7 566 289 (11127566289)
11 12 8 636 401 (11128636401)
F10 550i early N63 through 06/2013
11 12 7 566 288 (11127566288)
11 12 7 566 289 (11127566289)
11 12 8 636 401 (11128636401)
F10 550i N63N from 10/2012
11 12 7 614 700 (11127614700)
11 12 7 614 701 (11127614701)
11 12 5 884 16
F01 750i early N63 through 06/2012
11 12 7 566 288 (11127566288)
11 12 7 566 289 (11127566289)
11 12 8 636 401 (11128636401)
F01 750i N63N from 05/2011
11 12 7 614 700 (11127614700)
11 12 7 614 701 (11127614701)
11 12 5 884 16
Cover perimeter bolts (ASA M6)
07 12 9 907 367 (07129907367)
Catalog qty 34 for both covers.
Oil filler neck O-ring (right bank)
07 11 9 906 276 (07119906276)
Replace at reinstall. Neck for these BMWs: 11 12 7 507 224 (11127507224).
Camshaft sensor O-rings
12 14 1 748 398 (12141748398)
Catalog quantity 4.
Inner cover seals (N63 only)
Replace on install on each bank. N63O1 uses renewed profile seals at the cover instead.
High-pressure pump service
New pump screws and sealing ring when the pump comes off.
Injectors on this job
New Teflon ring and decoupling element each time. Do not reuse the decoupling element you remove.
Out in this order (one bank at a time)
- Batterynegative left bank, positive release right bank
- Acoustic cover
- Charge air pathleft CAC and intake; right intercooler
- Coolant hardwareexpansion tank left; drain right bank
- Fuel feed lineleft bank
- Injector harness moved
- Coils and injectorscyl 5-8 left, 1-4 right
- High-pressure pump
- Oil filler neckright bank only
- N63O1 extrascats, vacuum pump, shields
- Cylinder head coverbolts 17 to 1 or 16 to 1 on N63O1
Steps, torque values and part rules come from BMW's repair instructions for N63 cylinder head cover gaskets. Part numbers come from BMW's parts catalog up to 2020. Check yours by VIN.

- Cover bolt 17
- Cover bolt 1
- Cover bolt 9
- Cylinder head cover
Tools
Socket set and extensions
Reach cover perimeter bolts and charge-air fasteners.
Torque wrench
Fuel line lock caps
Required whenever HP lines are open.
Drain pan and coolant fill gear
Right bank drain, then fill and vent when that side is buttoned up.
Jack and stands or a lift
Stable support before you work under the wheel arch on the right bank.
Steps
-
Disconnect the battery
Left bank: disconnect the negative terminal. Right bank: release the positive terminal after you are ready for that side's fuel and coolant work.
Caution: no charger on the jump-start terminal while HP fuel lines are open.
-
Remove acoustic cover
Pull the engine acoustic cover only when under-hood temperature is above 20 degrees C.
Caution: at reinstall use distilled water on the seal only, no grease.
-
Open the charge-air path

- Charge air cooler connector
- Charge air cooler screw
- Charge air cooler mounting screws
- Throttle valve clamp
Left bank: remove the left charge air cooler, intake filter housing, expansion tank, and coolant valve for the heater feed line. Right bank: remove the right intercooler.
-
Right bank: drain coolant
Drain the cooling system before fuel or cover work on the right bank.
Caution: coolant must be below 40 degrees C before HP fuel line work.
-
Left bank: fuel line
Disconnect the fuel feed line on the left bank and cap open HP lines immediately.
Caution: wear PPE. Fuel can discharge at high speed.
-
Move injector wiring
Detach the injector wiring harness on the bank you are opening so harness clips clear the cover.
-
Coils and injectors off
Remove ignition coils and injectors for that bank: cylinders 5-8 on the left, 1-4 on the right.
Caution: keep fuel off the coil silicone boot and do not yank a coil straight out.
-
Remove HP pump
Remove the high-pressure pump on that bank. Bag the mounting screws; they are single-use on reinstall.
-
Right bank: oil filler neck
On the right bank, remove the oil filler neck before you loosen cover perimeter bolts. Renew its O-ring at reinstall.
-
N63O1: extra access
N63O1 right: remove the vacuum pump and the catalytic converter for cylinders 1-4, and renew the vacuum pump lubrication sealing ring. N63O1 left: remove catalytic converters on both sides before cover bolts.
-
Loosen cover bolts
Loosen perimeter bolts in reverse numbered order: 17 to 1 on N63 each bank, 16 to 1 on N63O1. Lift off the cylinder head cover.
-
Clean sealing surfaces
Clean the cylinder head and cover sealing surfaces before any new gasket touches metal.
-
Install new gaskets

- Profile gasket on the cover
On N63, fit new profile gaskets and inner cover seals. On N63O1, renew both profile seals at the cover. Match gasket numbers to your BMW row above.
-
Positioning screw first

- Camshaft sensor positioning screw
Install the camshaft sensor positioning screw: one screw on N63 each bank, screws 15 and 16 on N63O1. Snug it, then release 90 degrees before final cover torque.
-
Two-stage bolt torque
Tighten cover bolts in two work steps to 10 Nm, sequence 1 to 17 on N63 and N63O1 left, 1 to 16 on N63O1 right.
Caution: tighten in the numbered sequence for both work steps.
-
Reinstall HP pump
Fit a new HP pump sealing ring and new mounting screws. Torque the pump to 12 Nm. Turn the engine by hand at the crankshaft bolt in the correct rotation only when the pump needs alignment.
-
Reinstall injectors
Install each injector with a new Teflon ring and a new decoupling element. Torque the hold-down to 14 Nm. Finish install within 10 minutes of seating the ring or cap the tip.
-
Coils, fuel, wiring
Reinstall coils, reconnect fuel on the left bank, and route the injector harness. Torque every injector and harness ground screw you removed at 10 Nm where they are M6 ground points.
-
Right bank: filler neck
Install the oil filler neck with a new O-ring and torque to 10 Nm.
-
Charge air and cooling
Reinstall charge-air parts on both sides. On the right bank, fill and vent the cooling system.
-
Acoustic cover and battery
Reinstall the acoustic cover above 20 degrees C, then reconnect the battery terminal you opened for that bank.
-
Repeat the other bank
Run the same sequence on the opposite bank with its own gasket set.
Torque specs
Read the full guide free
Two quick answers open the rest of the steps.
Now find the part.
Search by chassis or engine, or browse the whole catalog