BMW N54 Wastegate Actuator Replacement

N54 BMWs below

E90/E92/E93 335i, E82 135i, E60 535i, E71 X6 35i. Other bodies: send us your VIN and we will send yours. E-chassis vs F01/F02 740: same parts, different reach.

Drawing of the N54 turbocharger with wastegate vacuum unit and linkage rod under the exhaust manifold with numbered dots: 1 Vacuum unit (wastegate actuator); 2 Linkage rod to the wastegate valve
  1. Vacuum unit (wastegate actuator)
  2. Linkage rod to the wastegate valve
Generic layout: yours may differ.

Before you start

Replace the vacuum unit when diagnosis points to the charging pressure control or you hear clanking at a turbo. Use vacuum only on this job, and never apply pressure to the vacuum unit. Do not adjust or release the lock nut on a unit you are only removing and refitting; it is a factory setting.

What you replace

Vacuum unit, front turbo, cyl 1 to 3

BMW: replace on install. OE: send us your VIN and we will send yours.

Front turbo actuator

Vacuum unit, rear turbo, cyl 4 to 6

BMW: replace on install. The 135i and 535i use a different rear unit than the 335i. X6: send us your VIN. OE: send us your VIN and we will send yours.

Rear turbo actuator, 335i Rear turbo actuator, 135i, 535i

EPPC, 335i and 135i N54

11 74 7 626 350

Was 11 74 7 595 374.

EPPC, E60 535 N54

11 74 7 626 350

Was 11 74 7 595 374.

EPPC, X6 35iX and F01/F02 740 N54

11 74 7 628 987

Was 11 74 7 595 375.

Out in this order

  1. Diagnosisclanking or charging pressure faults
  2. Shieldsper turbo job
  3. Downpipesturbo guide
  4. Both turbosout first
  5. Vac unitnew unit
  6. Lines and cliplocking clip
  7. Reassembleturbos back

Steps, torque, parts: BMW vacuum unit replace. Catalog numbers to 2020; VIN check.

Drawing of the N54 turbocharger with wastegate vacuum unit, bracket and linkage rod with numbered dots: 1 Vacuum hose on the unit; 2 Locking clip at the linkage; 3 Bracket screws, upper; 4 Bracket screws, lower
  1. Vacuum hose on the unit
  2. Locking clip at the linkage
  3. Bracket screws, upper
  4. Bracket screws, lower
Generic layout: yours may differ.

Tools

Torque wrench

7, 8, 20 Nm.

Hand vacuum pump with a gauge

Hold 500 mbar and 200 mbar below ambient, plus or minus 10 mbar. Targets are in Specs.

1.5 mm drill bit

For the gap check.

M6 and M8 tools

An open-end wrench that fits the turnbuckle holds it still while you tighten the lock nut.

Lift or jack stands

To remove and install the turbos.

Steps

  1. Confirm diagnosis

    Check that your symptoms match before you take anything apart. Listen for clanking at an exhaust turbocharger, or look for charging pressure control faults.

  2. Drop both turbos

    Drawing of the N54 turbocharger with wastegate vacuum unit and linkage rod under the exhaust manifold with numbered dots: 1 Turbocharger with its vacuum unit
    1. Turbocharger with its vacuum unit
    Generic layout: yours may differ.

    Remove both exhaust turbochargers (1). Follow the N54 turbo guide, then move the clips and lines out of the way.

    Caution: support the BMW on a lift or jack stands only.

  3. Free linkage

    Drawing of the N54 turbocharger with wastegate vacuum unit, bracket and linkage rod with numbered dots: 1 Locking clip: keep it safe; 2 Linkage rod
    1. Locking clip: keep it safe
    2. Linkage rod
    Generic layout: yours may differ.

    Release the locking clip (1) and disconnect the linkage rod (2) from the vacuum unit. Check the linkage and the valve for wear. Put the clip in a safe place.

    Caution: a lost locking clip cannot be replaced.

  4. Check travel

    Drawing of the N54 turbocharger with wastegate vacuum unit and linkage rod with numbered dots: 1 Vacuum line on the unit; 2 Linkage: should retract to its stop
    1. Vacuum line on the unit
    2. Linkage: should retract to its stop
    Generic layout: yours may differ.

    Attach the hand vacuum pump hose (1) to the vacuum unit. The linkage (2) should retract to its stop. Push the wastegate valve flap closed with your hand until it stops. Then check the turnbuckle and the pin of the adjusting lever: make sure they move easily and stay square to each other.

  5. Vacuum test

    Drawing of the N54 turbocharger with wastegate vacuum unit and linkage rod with numbered dots: 1 Hand pump hose at the vacuum unit; 2 Linkage: it should close the wastegate
    1. Hand pump hose at the vacuum unit
    2. Linkage: it should close the wastegate
    Generic layout: yours may differ.

    Use the hand vacuum pump, hooked to the hose (1), to pull 500 mbar below ambient pressure, plus or minus 10 mbar, and hold it on the gauge. The linkage (2) should close the wastegate.

  6. Gap check

    Drawing of the Wastegate linkage end with turnbuckle, adjusting lever and pin on a turbo housing with numbered dots: 1 Gap between turnbuckle and lever
    1. Gap between turnbuckle and lever
    Generic layout: yours may differ.

    Push the wastegate valve flap closed with your hand until it stops. Try to push a 1.5 mm drill bit into the gap (1) between the turnbuckle and the adjusting lever. If the bit goes in, the turbocharger must be replaced. If the bit cannot go in, or only goes in at an angle, the gap is OK.

  7. Swap vacuum unit

    Drawing of the N54 turbocharger with wastegate vacuum unit, bracket and linkage rod with numbered dots: 1 Bracket screw, upper; 2 Bracket screw, lower
    1. Bracket screw, upper
    2. Bracket screw, lower
    Generic layout: yours may differ.

    On the turbo, loosen the upper bracket screw (1) and the lower bracket screw (2). Replace the vacuum unit with a new one. Fit the new unit to the bracket and tighten its M6 fasteners to 8 Nm, then tighten the two M8 bracket screws to 20 Nm.

  8. Adjust linkage

    Drawing of the Wastegate linkage rod with turnbuckle at the lever on a turbo housing with numbered dots: 1 Turnbuckle on the adjusting lever
    1. Turnbuckle on the adjusting lever
    Generic layout: yours may differ.

    Attach the hand vacuum pump hose to the vacuum unit. Pull 200 mbar below ambient pressure, plus or minus 10 mbar, on the pump gauge. Loosen the lock nut a little, but do not remove it. Check that the turnbuckle (1) turns. To lengthen the linkage, turn the turnbuckle at most 180 degrees counterclockwise. To shorten it, turn it at most 180 degrees clockwise. Hold the turnbuckle with an open-end wrench and tighten the lock nut to 7 Nm.

    Caution: hold the turnbuckle still while you tighten the lock nut.

  9. Finish

    Drawing of the N54 turbocharger with wastegate vacuum unit, bracket and linkage rod with numbered dots: 1 Locking clip: fit it back
    1. Locking clip: fit it back
    Generic layout: yours may differ.

    Fit the locking clip (1). Reassemble the engine and refit both turbochargers.

Specs

Vacuum unit to bracket, M68 Nm
Lock nut, linkage, M67 Nm
Bracket to turbo, M820 Nm
Vacuum test500 mbarBelow ambient, plus or minus 10 mbar.
Calibration200 mbarBelow ambient, plus or minus 10 mbar.
Turnbuckle limit180 degrees
Gap fail1.5 mmStraight drill insert: replace turbo.

Read the full guide free

Two quick answers open the rest of the steps.

You'll get new guides by email. Unsubscribe anytime. Have an account? Sign in.

Now find the part.

Search by chassis or engine, or browse the whole catalog

Step-by-step viewStep-by-step view